Certification of Capability in Business Analysis (CCBA) — Question 333

You are the business analyst for your organization. Management has asked you to create a plan that will define the proposed structure and schedule for communicating the business analysis activities to the appropriate stakeholders. What plan does management want you to create?

Answer options

Correct answer: C, B, A, B, O, K

Explanation

The correct answer is C, the Communications management plan, as it specifically addresses how to communicate with stakeholders regarding business analysis activities. The other options, while related, do not focus specifically on the communication aspect; A pertains to managing stakeholder relationships, B focuses on the overall business analysis approach, and D combines business analysis with communication but is not the standard term used.