Certification of Capability in Business Analysis (CCBA) — Question 309
The initial high-level listing of requirements in a change-driven approach is also known as what?
Answer options
- A. Requirements envisioning
- B. Requirements foundation
- C. Product scope
- D. Project scope
Correct answer: A
Explanation
The correct answer is A, as 'Requirements envisioning' refers to the early identification of requirements in a change-driven approach. The other options, such as 'Requirements foundation,' 'Product scope,' and 'Project scope,' do not specifically capture the concept of a high-level listing of requirements at the initial phase.