Certification of Capability in Business Analysis (CCBA) — Question 293

You are the business analyst for your organization and you're working with the key stakeholders to validate the requirements. In your review, you have determined the business value of each requirement and you've discovered three requirements that do not deliver direct or indirect value to the stakeholders. What should you do with these requirements?

Answer options

Correct answer: D

Explanation

The correct action is to remove the requirements that do not add value, as they can clutter the project and waste resources. Justifying their existence or determining their purpose does not address the lack of value, and checking for integration with other requirements may still lead to maintaining unnecessary items in the requirements set.