Certification of Capability in Business Analysis (CCBA) — Question 292
When do change requests generally increase in a project?
Answer options
- A. Towards the beginning of the project.
- B. During the project scope management processes.
- C. During the project's launch.
- D. Towards the end of the project.
Correct answer: D
Explanation
Change requests are most common towards the end of a project as stakeholders review the final outcomes and may identify additional needs or adjustments. In contrast, changes at the beginning or during the launch are typically related to initial planning and scope definition, while scope management processes focus on controlling changes rather than generating them.