Certification of Capability in Business Analysis (CCBA) — Question 239
A business analyst (BA) is in the process of specifying the confirmed results of a requirements elicitation workshop. Which of the following help to ensure that the correct information about the requirements is provided to the participants?
Answer options
- A. Standard templates and syntax
- B. Requirements architecture
- C. Stakeholder list
- D. Roles and permissions matrix
Correct answer: C
Explanation
The correct answer is C, as a stakeholder list identifies all individuals involved in the project, ensuring that the right people receive the relevant information about requirements. Options A, B, and D are useful for documentation and management but do not directly ensure that accurate information about requirements reaches the participants.