Certification of Capability in Business Analysis (CCBA) — Question 229

Stakeholders initially agreed to an implementation schedule for a set of reports based on the value to business users. The development team provided a detailed estimate of the time required to develop each report based on the business requirements. What should the business analyst (BA) and the stakeholders do with the estimates?

Answer options

Correct answer: C

Explanation

The correct answer is C because the development team's estimates may indicate that the initial business requirements are unrealistic or need adjustment to align with the available resources. Options A, B, and D do not directly address the need to modify the requirements based on the time estimates provided.