Certification of Capability in Business Analysis (CCBA) — Question 224
A business owner has marked certain requirements as high priority for the upcoming release. After performing some analysis, the project team concluded that some of these requirements are not actually high priority and can be implemented in later releases. How should the project team proceed with prioritizing requirements?
Answer options
- A. Consult with the business owner to discuss possible trade-offs
- B. Execute the requirements that the business owner identified
- C. Implement the requirements that the project team considers important
- D. Change the priority of the requirements by performing a re-ranking
Correct answer: A
Explanation
The correct approach is to consult with the business owner to discuss possible trade-offs (Option A), as this ensures alignment between the team's analysis and the owner's expectations. Option B is incorrect because it disregards the team's findings, while Option C overlooks the business owner's priorities. Option D may not involve the business owner directly, which is essential in this context.