Certification of Capability in Business Analysis (CCBA) — Question 168

Requirements have been prioritized in the product backlog for inclusion in the upcoming release. One of the project team members fears that at least one requirement from the prioritization list is not finalized and still requires further analysis. Which of the following factors describe the affected requirement?

Answer options

Correct answer: D

Explanation

The correct answer is D, Risk, as it pertains to uncertainties that may affect the project's success if not addressed. The other options, such as Benefit, Dependency, and Stability, do not specifically capture the concern regarding the requirement's incomplete analysis and potential impact on the project.