Certification of Capability in Business Analysis (CCBA) — Question 141
Stakeholders need a financial report that can be published and distributed to multiple end users. They would also like the report to be developed within a specific time frame and within cost. What must the business analyst (BA) do to achieve this goal?
Answer options
- A. Review the project budget
- B. Revise business requirements
- C. Define solution approaches
- D. Update the project schedule
Correct answer: A
Explanation
The correct answer is A, as reviewing the project budget is essential to ensure that the report can be developed within the financial constraints set by the stakeholders. Options B, C, and D do not directly address the financial aspect which is critical for meeting the stakeholders' needs.