Certified Business Analysis Professional (CBAP) — Question 55

In a requirements management effort, the business analyst (BA) has reviewed all the requirements and has completed assessing the various impacts of changes to some of the requirements. The BA is planning to share the impact of the changes to all the stakeholders and obtain a consensus in resolution of some of the changes. Which technique will help the BA obtain a resolution on the impact of the requirement changes?

Answer options

Correct answer: B

Explanation

Workshops are effective for bringing stakeholders together to discuss and resolve issues collaboratively, making them ideal for reaching consensus on requirement changes. Focus groups, interviews, and surveys, while useful for gathering input, do not facilitate the same level of interactive discussion and consensus-building that workshops do.