Certified Business Analysis Professional (CBAP) — Question 419
The ____, an output of the define scope process, does document the process and criteria for accepting completed products.
Answer options
- A. Statement of Work
- B. Contract
- C. Project scope statement
- D. Project management plan
Correct answer: C
Explanation
The correct answer is C, the Project scope statement, as it specifically details the process for acceptance of completed deliverables. Options A and B pertain to agreements and contracts, while D refers to a comprehensive plan that includes more than just the scope.