Certified Business Analysis Professional (CBAP) — Question 419

The ____, an output of the define scope process, does document the process and criteria for accepting completed products.

Answer options

Correct answer: C

Explanation

The correct answer is C, the Project scope statement, as it specifically details the process for acceptance of completed deliverables. Options A and B pertain to agreements and contracts, while D refers to a comprehensive plan that includes more than just the scope.