Which of the following processes can start with the source of problems or with the problem itself?
Answer options
- A. Risk estimation
- B. Risk analysis
- C. Risk management
- D. Risk identification
Correct answer: D
Explanation
The correct answer is D, Risk identification, as it specifically focuses on recognizing and defining problems, which can stem from their source or the problems themselves. The other options, while related to risk, involve further steps in the process after problems have already been identified.