Certified Business Analysis Professional (CBAP) — Question 404
When can changes to requirements occur in a business analysis planning and monitoring assignment?
Answer options
- A. Change to requirements can occur any time before the project scope statement is created.
- B. Changes to requirements can occur at any time.
- C. Changes to requirements can occur any time after the project's change control system has been enacted.
- D. Change to requirements can occur at any time before the key stakeholders approve the identified requirements.
Correct answer: B
Explanation
The correct answer, B, indicates that changes to requirements can happen at any point in the project, allowing for flexibility. Option A is incorrect because it restricts changes to a specific timeframe before the project scope statement. Option C incorrectly suggests changes can only occur after the change control system is in place, and option D limits changes to only before stakeholder approval, which does not reflect the ongoing nature of requirements management.