Certified Business Analysis Professional (CBAP) — Question 403
When is stakeholder analysis performed?
Answer options
- A. As soon as the project charter is created.
- B. As soon as the project sponsor is named.
- C. As soon as a business need is identified.
- D. As soon as a business solution is identified.
Correct answer: C
Explanation
The correct answer is C because stakeholder analysis is crucial once a business need is identified to understand who will be affected and involved in the project. Options A and B are incorrect as they focus on project initiation phases rather than the identification of business needs. Option D is also incorrect because stakeholder analysis should precede the identification of a solution.