Certified Business Analysis Professional (CBAP) — Question 371
Which of the following is a narrative description of the work required for the project?
Answer options
- A. Contract work breakdown structure (CWBS)
- B. Work breakdown structure (WBS)
- C. Contract statement of work (CSOW)
- D. Statement of work (SOW)
Correct answer: D
Explanation
The correct answer is D, Statement of work (SOW), as it provides a narrative description of the project's work requirements. The other options, while related to project management, do not serve as narrative descriptions; CWBS and WBS focus on task organization, and CSOW relates specifically to contract terms.