Certified Business Analysis Professional (CBAP) — Question 36
Which of the following is a graphical representation of roles and responsibilities of different project team members?
Answer options
- A. RACI chart
- B. Pareto chart
- C. Resource histogram chart
- D. Organization chart
Correct answer: A
Explanation
The correct answer is the RACI chart, as it specifically identifies and clarifies roles and responsibilities within a project. The Pareto chart focuses on identifying the most significant factors in a dataset, the Resource histogram chart displays resource allocation over time, and the Organization chart shows the structure of an organization but does not detail roles in project contexts.