Certified Business Analysis Professional (CBAP) — Question 36

Which of the following is a graphical representation of roles and responsibilities of different project team members?

Answer options

Correct answer: A

Explanation

The correct answer is the RACI chart, as it specifically identifies and clarifies roles and responsibilities within a project. The Pareto chart focuses on identifying the most significant factors in a dataset, the Resource histogram chart displays resource allocation over time, and the Organization chart shows the structure of an organization but does not detail roles in project contexts.