Certified Business Analysis Professional (CBAP) — Question 347

There are four inputs to the plan business analysis activities.
Which one of the following is not an input to the plan business analysis activities process?

Answer options

Correct answer: A

Explanation

The correct answer is A because the 'List of identified risks' is not an input for the planning phase of business analysis activities. The other options, such as 'Organizational process assets', 'Business analysis approach', and 'Stakeholder list, roles, and responsibilities', are essential inputs that help guide the planning process.