Certified Business Analysis Professional (CBAP) — Question 329
Which of the following is a visual decomposition of the program scope and the resources needed in order to create the things defined within the program scope?
Answer options
- A. Resource breakdown structure (RBS)
- B. product breakdown structure (PBS)
- C. Budgeted Cost of Work Scheduled (BCWS)
- D. Work Breakdown Structure (WBS)
Correct answer: D
Explanation
The correct answer is D, Work Breakdown Structure (WBS), as it visually decomposes the project scope into manageable sections and details the resources required. Options A and B refer to specific breakdown structures that focus on resources and products respectively, while C relates to budgeting and scheduling rather than scope decomposition.