Certified Business Analysis Professional (CBAP) — Question 326
Which of the following is a flowchart that shows all the processes and the interfaces that interact with the project processes?
Answer options
- A. Process configuration
- B. Pareto chart
- C. Control chart
- D. Quality baseline
- E. RACI chart
Correct answer: A
Explanation
The correct answer is A, Process configuration, as it specifically represents the arrangement of processes and their interfaces in a project. The other options, such as Pareto chart and Control chart, serve different purposes, such as identifying issues or tracking performance over time, but do not depict the flow of processes in relation to project management.