Certified Business Analysis Professional (CBAP) — Question 325
There are just three inputs to the assess proposed solution process.
Which of the following is NOT one of the inputs for the assess proposed solution process?
Answer options
- A. Requirements
- B. Decision analysis
- C. Assumptions and constraints
- D. Solution options
Correct answer: B
Explanation
The correct answer is B, as decision analysis is not considered one of the primary inputs in the assess proposed solution process. The inputs typically include requirements, assumptions and constraints, and solution options, which are crucial for evaluating the proposed solutions effectively.