Certified Business Analysis Professional (CBAP) — Question 32

Which of the following is a table of all stakeholders showing the mapping of which stakeholders will contribute information to other stakeholders?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Communications Requirements Matrix, which specifically outlines the information flow between stakeholders. Option A, the RACI Chart, defines roles and responsibilities but does not map information sharing. Option C, the Project scope statement, details project deliverables and boundaries rather than stakeholder communication. Option D, the Organizational Breakdown Structure, represents the project's organizational hierarchy and does not focus on communication mapping.