Which of the following is a method of displaying the timelines of all the various subtasks that are involved in any project?

Answer options

Correct answer: C

Explanation

The correct answer is C, as an Activity network diagram effectively visualizes the relationships and timelines of various project subtasks. Options A and B, pie chart and scatter chart, are used for different types of data representation, while D, cost-benefit analysis, focuses on comparing the costs and benefits rather than displaying timelines.