Certified Business Analysis Professional (CBAP) — Question 280
Which of the following is the comparison of planned project results with actual project results?
Answer options
- A. Variance analysis
- B. Cost-benefit analysis
- C. Statistical Sampling
- D. Trend analysis
Correct answer: A
Explanation
Variance analysis is the process of evaluating the difference between planned and actual results, making it the correct answer. Cost-benefit analysis assesses the financial implications of projects, statistical sampling involves selecting a subset of data for analysis, and trend analysis focuses on patterns over time rather than direct comparisons of planned versus actual outcomes.