Certified Business Analysis Professional (CBAP) — Question 279
Which of the following is the formal acceptance of the project?
Answer options
- A. A project review
- B. A sign-off
- C. Risk assessment
- D. Inspection trend analysis
Correct answer: B
Explanation
The correct answer is B, as a sign-off signifies that the project has been formally accepted by the stakeholders. Options A, C, and D do not represent formal acceptance; a project review is an evaluation, risk assessment focuses on identifying potential issues, and inspection trend analysis examines data trends rather than approval.