Certified Business Analysis Professional (CBAP) — Question 28
The business analyst (BA) is preparing to determine the impact of various risks associated with the business analysis effort currently underway.
Which of the following would the BA use as an input into the assessment of risk?
Answer options
- A. Defined change strategy
- B. Analysis of potential value of the recommended solution
- C. List of prioritized requirements
- D. Unconfirmed results of elicitation activities
Correct answer: C
Explanation
The correct answer is C, as a List of prioritized requirements provides essential information on what needs to be delivered and helps assess the impact of risks on project objectives. The other options, while relevant to the project, do not directly inform the risk assessment process as clearly as the prioritized requirements do.