Certified Business Analysis Professional (CBAP) — Question 251
Which of the following phases is the first step towards creating a business continuity plan?
Answer options
- A. Business Continuity Plan Development
- B. Scope and Plan Initiation
- C. Business Impact Assessment
- D. Plan Approval and Implementation
Correct answer: B
Explanation
The correct answer is B, Scope and Plan Initiation, as this phase sets the foundation for the entire business continuity planning process. Options A, C, and D represent later stages in the process, which cannot be effectively executed without first establishing the scope and initiating the plan.