____ is a process to determine the completeness of the project work and to gain the customer's acceptance to move the project forward.
Answer options
- A. Phase gate review
- B. Inspection of key results
- C. Verify scope
- D. Quality control
Correct answer: D
Explanation
Quality control is essential for ensuring that the project's deliverables meet the required standards and obtaining customer acceptance. The other options do not specifically address the need for customer approval or the assessment of project work completeness in the same way that quality control does.