Certified Business Analysis Professional (CBAP) — Question 231
Which of the following chart shows the correlation between project team members and the work they've been assigned to complete?
Answer options
- A. Pie chart
- B. Responsibility Assignment Matrix (RAM) chart
- C. Gantt chart
- D. RACI chart
Correct answer: B
Explanation
The Responsibility Assignment Matrix (RAM) chart is specifically designed to map team members to their respective tasks, indicating who is responsible for what. The other options, such as pie charts and Gantt charts, do not serve this purpose; pie charts display proportions, while Gantt charts focus on scheduling rather than responsibilities.