Certified Business Analysis Professional (CBAP) — Question 113

You are the business analyst for your organization and are working with Ralph who is also a business analyst at your company. You have moved one of the requirements higher in the prioritization of the requirements because it is needed to be implemented before some of the more important requirements are done.
Ralph disagrees with your placement of the requirement because you are to rank the requirements based on their level of difficulty.
Who is correct and why?

Answer options

Correct answer: B

Explanation

You are correct because prioritizing the requirements based on their need for implementation is crucial; lower priority requirements must be completed to enable the execution of higher priority ones. Ralph's perspective on ranking by difficulty does not align with the current project's needs. Thus, option B is the correct choice.