IBM Tivoli Monitoring V6.3 Implementation — Question 83
A company is using Process Flow Control and wants to change the default values for Flow Start and Flow Complete statuses.
Where can these values be configured?
Answer options
- A. System Properties
- B. Work Type settings
- C. WOSTATUS Domain
- D. Change Work Order Options action
Correct answer: B
Explanation
The correct answer is B, as the default values for Flow Start and Flow Complete statuses are specifically configured in the Work Type settings. Options A, C, and D do not pertain to the configuration of these particular statuses, making them incorrect choices.