IBM Tivoli Monitoring V6.3 Implementation — Question 82
A supervisor is required to report actual work hours by work order number.
With which statuses can this be accomplished? (Choose two.)
Answer options
- A. INPRG
- B. WAPPR
- C. CANCEL
- D. PNDREV
- E. COMPLETE
Correct answer: A, E
Explanation
The statuses INPRG and COMPLETE are the only ones that allow for reporting actual work hours against a work order number. INPRG indicates ongoing work, while COMPLETE signifies that the work has been finalized, making both suitable for this requirement. The other statuses, such as WAPPR, CANCEL, and PNDREV, do not indicate that work has been performed or completed.