IBM Tivoli Monitoring V6.3 Implementation — Question 52
A company has assets at multiple locations that require maintenance. There is a requirement to have a single work order with charges rolled up to a single GL account.
How can that be achieved?
Answer options
- A. Create a task work order for each asset.
- B. Create a child work order for each asset.
- C. Add a job plan that has the assets associated.
- D. Add the assets in Multiple Assets, Locations and Cls.
Correct answer: B
Explanation
The correct answer is B because creating a child work order for each asset allows for all charges to be consolidated under a single work order while still tracking individual asset maintenance. Option A is incorrect as task work orders do not allow for this level of consolidation. Option C does not directly address the requirement for work order consolidation, and option D involves a different method of asset management without focusing on work order linkage.