IBM Tivoli Monitoring V6.3 Implementation — Question 51
A supervisor has a requirement in Labor Reporting to report labor hours for work that has been completed.
What are the options available to report labor?
Answer options
- A. labor, craft, company, and work order
- B. labor, crew, vendor/contract, work order and ticket
- C. labor, crew, vendor/contract, work order and ticket group
- D. labor, crew, vendor/contract, work order, activity and task
Correct answer: A
Explanation
The correct answer is A, as it lists the essential components needed for labor reporting in this context. Options B, C, and D include additional elements that are not specified as required for the supervisor's reporting needs, making them less relevant for this particular scenario.