IBM MQ v9.2 System Administration — Question 24
Which field on a Work Order is used to only schedule work during working time?
Answer options
- A. Flow Action Assist
- B. Split Shift
- C. Constrain to Shift
- D. Interruptible
Correct answer: C
Explanation
The correct answer is C, 'Constrain to Shift', as it specifically ensures that work is scheduled within designated working hours. The other options do not enforce this restriction; for example, 'Flow Action Assist' pertains to workflow management, 'Split Shift' refers to dividing work periods, and 'Interruptible' allows work to be paused, none of which relate to scheduling constraints.