IBM MQ v9.2 System Administration — Question 24

Which field on a Work Order is used to only schedule work during working time?

Answer options

Correct answer: C

Explanation

The correct answer is C, 'Constrain to Shift', as it specifically ensures that work is scheduled within designated working hours. The other options do not enforce this restriction; for example, 'Flow Action Assist' pertains to workflow management, 'Split Shift' refers to dividing work periods, and 'Interruptible' allows work to be paused, none of which relate to scheduling constraints.