IBM MQ v9.2 System Administration — Question 23

In the Purchase Requisitions application and with default settings, what status does the Purchase Requisition change to when all of its lines have been copied to a Purchase Order or a Contract?

Answer options

Correct answer: C

Explanation

The correct status is CLOSE, which indicates that the Purchase Requisition is no longer active because all lines have been successfully moved. INPRG, COMPLETE, and APPR do not accurately reflect the final state of a Purchase Requisition that has fulfilled its purpose by being copied to a Purchase Order or Contract.