Certified Scrum Master (CSM) – GAQM — Question 8
You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite for the Sprint Review to demo the items completed in the Sprint. Who should you invite as a required attendee to the Sprint Review?
1. Product Owner(s)
2. Development Team
3. Business Users
Answer options
- A. 1, 2, and 3
- B. 1 and 2 only
- C. The entire company
- D. 1 only
Correct answer: B
Explanation
The correct answer is B because the Product Owner and the Development Team are essential for the Sprint Review, as they are directly involved in the project's progress and deliverables. Business Users, while they may provide valuable feedback, are not required attendees for this meeting, making options A, C, and D incorrect.