Certified Scrum Master (CSM) – GAQM — Question 7

Which statement below best describes the primary objective of the Sprint Review?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the Sprint Review is designed to present the work done during the Sprint and gather feedback specifically from the Product Owner(s), who are key stakeholders. Options A, C, and D incorrectly specify the audience for feedback or misrepresent the purpose of the review, which is not primarily about senior management, the Scrum Master, or recommending future improvements.