Certified Scrum Master (CSM) – GAQM — Question 55

What is the major difference between Product Backlog and Sprint Backlog?

Answer options

Correct answer: C

Explanation

The correct answer is C because the Sprint Backlog is specifically derived from and contains selected items from the Product Backlog that the team plans to work on during a Sprint. Option A is incorrect as they are not equal; the Product Backlog is a broader list. Option B is wrong because the Product Backlog is not a subset of the Sprint Backlog, and D is incorrect since the Sprint Backlog is owned by the development team, not solely by the Product Owner.