Certified Scrum Master (CSM) – GAQM — Question 55
What is the major difference between Product Backlog and Sprint Backlog?
Answer options
- A. The Product Backlog is equal to the Sprint Backlog
- B. The Product Backlog is a subset of the Sprint Backlog
- C. The Sprint Backlog is a subset of the Product Backlog
- D. The Sprint Backlog is owned by the Product Owner
Correct answer: C
Explanation
The correct answer is C because the Sprint Backlog is specifically derived from and contains selected items from the Product Backlog that the team plans to work on during a Sprint. Option A is incorrect as they are not equal; the Product Backlog is a broader list. Option B is wrong because the Product Backlog is not a subset of the Sprint Backlog, and D is incorrect since the Sprint Backlog is owned by the development team, not solely by the Product Owner.