Certified Scrum Master (CSM) – GAQM — Question 54

Who defines the Sprint Backlog scope?

Answer options

Correct answer: B

Explanation

The Development Team is the one that defines the scope of the Sprint Backlog as they are the ones who will be doing the work. The Product Owner provides the vision and priorities, but the actual tasks and scope are determined by the team itself. The Scrum Master facilitates the process, and stakeholders provide input but do not define the backlog scope.