Certified Scrum Master (CSM) – GAQM — Question 43

Which of these may a Development Team deliver at the end of a Sprint (choose 2)?

Answer options

Correct answer: A, D

Explanation

Option A is valid because if the Product Owner specifically requests a document, it can be delivered. Option D is correct as it emphasizes delivering a complete increment of working software that meets the definition of 'done.' Options B and C are incorrect since delivering software with known bugs or failing tests does not align with the goals of a Sprint's completion.