Certified Scrum Master (CSM) – GAQM — Question 42
When many Scrum Teams are working on a project, what best describes the definition of "done"?
Answer options
- A. All teams must use the same definition
- B. Each Team defines and uses its own
- C. Each Team uses its own but must make it clear to all other Teams
- D. It depends
Correct answer: A
Explanation
The correct answer is A, as having a unified definition of 'done' ensures consistency and clarity across all Scrum Teams, which is crucial for effective collaboration. Options B and C suggest that teams can operate with different definitions, which can lead to misunderstandings and integration challenges. Option D implies ambiguity, which is not conducive to the Scrum framework's emphasis on transparency and alignment.