Certified Scrum Master (CSM) – GAQM — Question 36
What is the Release Burn down?
Answer options
- A. A graph indicating what has been completed by the Scrum Team
- B. A measure of the remaining Product Backlog across the time of a release plan
- C. What has been completed by the Scrum Team to date
- D. The work remaining to be completed by the Product Owner
Correct answer: B
Explanation
The correct answer, B, accurately describes the Release Burn down as it tracks the remaining Product Backlog over the duration of a release plan. Option A, while related, focuses on completed work rather than remaining tasks. Option C also refers to completed work, and option D incorrectly attributes remaining work to the Product Owner, rather than the overall Product Backlog.