Certified Scrum Master (CSM) – GAQM — Question 35
What happens when all committed items (requirements) are not completed at the end of the Sprint?
Answer options
- A. The Sprint duration is extended
- B. The tasks are determined to be unnecessary
- C. They return to the product backlog
- D. None of the above
Correct answer: C
Explanation
The correct answer is C because any incomplete items at the end of a Sprint are moved back to the product backlog for future consideration. Option A is incorrect, as extending the Sprint duration is not standard practice. Option B is also incorrect because the tasks may still hold value and simply need to be reprioritized.