What happens when all committed items (requirements) are not completed at the end of the Sprint?

Answer options

Correct answer: C

Explanation

The correct answer is C because any incomplete items at the end of a Sprint are moved back to the product backlog for future consideration. Option A is incorrect, as extending the Sprint duration is not standard practice. Option B is also incorrect because the tasks may still hold value and simply need to be reprioritized.