EXIN ITIL Foundation (legacy) — Question 2
Which process provides the Project Board with the information it requires in order to commit resources to the project?
Answer options
- A. Managing Product Delivery
- B. Initiating a Project
- C. Controlling a Stage
- D. Directing a Project
Correct answer: B
Explanation
The correct answer is B, as the Initiating a Project process is specifically designed to gather and present information needed for the Project Board to make resource commitments. The other options, such as Managing Product Delivery and Controlling a Stage, focus on execution and oversight rather than the initial resource allocation decision.