EXIN DevOps Foundation — Question 19
What is a correct use of a value stream map?
Answer options
- A. Identifying and eliminating bottlenecks in the process
- B. Inserting feedback from the customer into the process
- C. Visualizing the work that is done or is in process
Correct answer: C
Explanation
The correct answer is C, as a value stream map is primarily used to visualize the flow of work and identify tasks that are in progress or completed. Options A and B, while relevant to process improvement, do not directly pertain to the primary function of a value stream map.