EXIN DevOps Foundation — Question 18

The most valuable information of a value stream map is taken from three key metrics.
What is one of these three key metrics?

Answer options

Correct answer: B

Explanation

The correct answer is B, Percentage complete, as it provides insight into the progress of work in the value stream. Options A, C, and D, while relevant metrics, do not represent one of the three key metrics that are most valuable in the context of a value stream map.