EXIN Agile Scrum Foundation — Question 39

The team determines that it has over-committed itself for a Sprint.
Who should be present when reviewing and adjusting the Sprint work?

Answer options

Correct answer: C

Explanation

The correct answer is C because during a Sprint, the team itself is primarily responsible for managing its workload. While the Product Owner can provide input, the core review and adjustments should be made by the team to ensure they can meet their commitments effectively. Options A and B include additional roles that are not necessary for this specific task.