EXIN Agile Scrum Foundation — Question 38
Which of the following statements best expresses the role that the daily stand-up meeting plays in the monitoring of a Scrum project?
Answer options
- A. The stand-up meeting helps the Scrum Master to update the burn-down chart.
- B. The stand-up meeting gives the team insight into their progress and their issues.
- C. The stand-up meeting lets the Product Owner review the progress of the team.
Correct answer: B
Explanation
The correct answer, B, highlights that the stand-up meeting is crucial for teams to gain insights into their current progress and any obstacles they might be facing. Option A is incorrect because the stand-up meeting is not primarily for updating the burn-down chart, and option C is wrong as the meeting focuses more on the team rather than on the Product Owner's review.