EXIN Agile Scrum Foundation — Question 28

A large product team features six different teams having ten members each, working on a project that involves four high level features.
How many Product Backlogs should the team have?

Answer options

Correct answer: A

Explanation

The correct answer is A, as a single Product Backlog is typically maintained for the entire team to ensure alignment across all teams working on the same project. Having multiple backlogs could lead to inconsistencies and miscommunication among the teams, whereas a unified backlog helps prioritize and manage the development of the four high-level features effectively.