EXIN Agile Scrum Foundation — Question 27
The Product Owner is going on a three-week vacation. The team should be closing the current Sprint and starting a new Sprint at the end of the first week of the
Product Owner's vacation.
What is the best way to continue the Scrum rituals in this situation?
Answer options
- A. Each Scrum team should ideally have two Product Owners to provide cover.
- B. The Product Owner should be requested to delay his vacation by a week.
- C. The Scrum Master should take over and cover for the Product Owner.
Correct answer: C
Explanation
The best solution in this scenario is for the Scrum Master to step in and manage the responsibilities of the Product Owner, ensuring that Scrum rituals continue smoothly. Having two Product Owners is not practical and delaying the vacation is not a viable option, as personal plans should be respected.